Formula usedSlab = length × width × depth; solid round = π × diameter² ÷ 4 × height; hollow tube = π × (outside diameter² − inside diameter²) ÷ 4 × height. Order volume = shape volume × quantity × (1 + waste% ÷ 100). Bags = round up(order volume ÷ mixed yield per bag). Material cost = order volume × quoted price, or whole bags × bag price.
Your values in the formula5 m × 4 m × 0.15 m × 1 × (1 + 5%) = 3.15 m³.
Assumptions and rounding- Selected shape: slab. All dimensions convert to metres before calculation.
- Bag count rounds up using the mixed-concrete yield printed on your product, not its dry weight.
- Only entered prices are used. Delivery, labour, tax, supplier minimums and structural design are excluded.
Excavation tolerance, uneven sub-base, formwork, site access and supplier minimums can change the order. A qualified professional must approve structural work.